System Type: Solar PV
Including: 39 REC 410 AA PURE modules and Enphase IQ8PLUS-72-M-US inverters
System Capacity: 15.99 kW DC
Battery system: None

  • May 26: got 8 vendors with about 22 quotes with variation of size and panels mfg
  • June 12: sign contract with Blossom, install date estimate: late August/early September, price about $2.53/watt
  • June 16: completed the net metering application with PSE
  • June 30: PSE approval to construct
  • Mid July: install date of August 14
  • Late July: parts came in sooner, install date moved up to July 31
  • July 31-August 2: Blossom started install (own crew, not contractors)
  • August 3: City inspection pass
  • August 4: PSE “will now work to commission and interconnect your PV system” (it may take up to 30 business days)
  • September 2: PSE we are still working on it
  • September 9: PTO!!!

https://preview.redd.it/b35vl83qpnnb1.jpg?width=1182&format=pjpg&auto=webp&s=134589e47a72f3dc7b8cddad15ea825c8efe3389

https://preview.redd.it/w4io0s2qpnnb1.jpg?width=840&format=pjpg&auto=webp&s=830759fed4a463dfe7e489acdeba71a26d1b9a4a

submitted by /u/kasukeo
[link] [comments]

      



Author: AliensFaith
HighTech FinTech researcher, university lecturer & Scholar. He is studying his second doctoral degree at the Hague International University. Studying different fields of Sciences gave him a broad understanding of various aspects of life. His recent researches covered AI, Machine-learning & Automation concepts. The Information Technology Skills & Knowledge gave his company a higher position over other regional high-tech consultancy services. The other qualities and activities which can describe him are a Hobbyist Programmer, Achiever, Strategic Thinker, Futuristic person, and Frequent Traveler.

Discover more from Maheri Network

Subscribe now to keep reading and get access to the full archive.

Continue reading