I’ve submitted my quote for additional bids to energysage and am waiting on replies, but wanted to check here to see how my quote stacks up. Here’s the proposal:
45 Mitrex 405 Panels, ground mount w/65 ft of trench/wire
45 Enphase IQ8+ Inverters
3 Tesla Powerwall 2
18kw system, no SPAN.
$135k finalized quote after a solar survey, not taking into account the $40k 30% tax credit. Mitrex doesn’t have the panel price listed, but my guess is $400/panel is about right, inverters maybe $180 per, and Powerwall x3 $25k. $50k of equipment at retail cost not counting the wiring and mounts. After adding mounting, wiring, permitting, etc, my guess is there’s at least $75k left for labor.
I feel like maybe there’s some wiggle room for discounting, but probably not much is my guess. Thoughts?