PTO at last (PG&E)

Timeline:

12/6 contract signed with Solar Optimum

12/13 site survey complete

12/19 site layout designed

12/22 PG&E received application

1/9 PG&E sent NEM 2.0 agreement

2/21 City permits approved

3/1 Panels installed

3/22 Main panel upgrade

5/18 PG&E disconnect-reconnect

6/11 PTO complete

Total six months!

submitted by /u/joeverdrive
[link] [comments]      



Author: AliensFaith
HighTech FinTech researcher, university lecturer & Scholar. He is studying his second doctoral degree at the Hague International University. Studying different fields of Sciences gave him a broad understanding of various aspects of life. His recent researches covered AI, Machine-learning & Automation concepts. The Information Technology Skills & Knowledge gave his company a higher position over other regional high-tech consultancy services. The other qualities and activities which can describe him are a Hobbyist Programmer, Achiever, Strategic Thinker, Futuristic person, and Frequent Traveler.

Discover more from Maheri Network

Subscribe now to keep reading and get access to the full archive.

Continue reading

Exit mobile version